How long will my bathroom reno take?
Why does it take so long for us to do your bathroom when they can do it in a week on the TV?
Its a really good question and 1 we get asked all of the time. I don’t know about you but I would not want to live in a home that had its bathroom done in a week!
Your custom bathroom renovation will take 3 weeks. We then allow another 3-4 days AFTER that to have your custom shower screen to be installed.
Below is a rough breakdown of how the process will go……
DAY 1:
- Sign contract
- Run through plan and confirm layout. (Including lights, power points, heated towel rails, niches, recessed vanities and mirror cabinets, feature tiles, direction to lay tiles.
- All tiles & fixtures and fittings need to be onsite today.
- Strip bathroom and clean out
DAY 2:
- Plumber and electrician come in rough in for new appliances and fixtures
- Check all PC items specs and set out fittings to work tiles and spacing’s to suit bathroom
DAY 3:
- Cut in all niches and framework required (bath frame, new nib walls, recesses etc)
DAY 4:
- Line walls and Waterproof 1st coat
DAY 5:
- Waterproof 2nd coat
DAY 6:
- Tiler to start. Depending on the size of that bathroom he will establish number of days to tile bathroom
AFTER TILER COMPLETE:
- Plumber to fit fittings
- Measure up for custom shower screen
- Put up cornice
DAY 2:
- Electrician to do electrical fit-out
- Rough clean
- Silicone up bathroom
DAY 3:
- Professionally clean
- Inform clients when shower screen will be installed
- Do a walk through with client make sure that they are happy with everything job can be signed off
So that’s where all of the days in a bathroom reno disappear to.
But don’t worry – the wait will be worth it and you will have a beautiful and functioning bathroom for many years to come!